Project Construction & Staging

During the design process, it was decided that closures and detours of TH 19 and the I-35 Ramps should be minimized to the greatest extent. As a result of that decision, the project will be constructed in 6 stages during the project. The next pages will show the proposed staging of the project, estimated durations, and if any closures are proposed.

Please keep in mind that the Contractor may propose changes to the staging to aid in constructibility and/or to reduce the duration of the individual stage of the project.

Estimated construction durations are weather-dependent.

Click to enlarge staging maps

 

Stage 3B

Description:  Stage 3B will complete construction of CSAH 46 and the remaining items on the roundabout. TH 19, east of the roundabout, will be milled & overlayed.

Traffic Impacts:  CSAH 46 (Hazelwood Ave.) will remain closed. Flagging operations with temporary lane closures on TH 19 will occur during the mill and overlay portion of this stage. 

Detour:  None.

Estimated Duration:  2 weeks